Thank you for your interest in the US 1 Corridor Feasibility Study!

The Central Midlands Council of Governments (CMCOG) aims to address accommodations for growth and change along US 1. The project extent of 6.6 miles starts at Spears Creek Road / Bookman Road (S-53) and ends at Watts Hill Road (S-575). Your feedback is integral to the corridor’s continued success.

Corridor Challenges

Horizontal Curvature

Inadequate Clear Zones

Poor Sight Distance at Intersections

Traffic Congestion

Few Left-Turn Lanes

Parallel Railroad

Significant Planned Residential Development

Land Use Variations (Downtown Elgin vs Suburban)

Pedestrian Connectivity

The US 1 corridor within the study area limits carries 13,200 vehicles, with 3-5% heavy trucks.  With numerous residential and commercial developments planned in the coming years, it is a crucial time for CMCOG to prepare for the future of this corridor.

CMCOG is aiming to reduce crashes and traffic congestion along the corridor while minimizing right-of-way impacts. The project team, led by AECOM, is engaging the public, coordinating with stakeholders, gathering and analyzing land use and traffic data, and providing  recommended alternatives to address the issues within the project extent.

Please take our project survey.

Project Schedule

Project Kickoff

February, 2024

Public Meetings (4)

May, 2024

Steering Committee Alternatives Analysis Workshop

August 2024

Public Meeting (Show Alternatives)

October, 2024

Project Completion

December, 2024